A project has an Earned Value (EV) = $5, Actual Cost (AC) = $7 and both Cost
Fantastic news! We've Found the answer you've been seeking!
Question:
- A project has an Earned Value (EV) = $5, Actual Cost (AC) = $7 and both Cost Performance Index (CPI) and Schedule Performance Index (SPI) equal 0.90. The original project budget is $10. Assuming the remaining work will be impacted by the current cost performance and current schedule performance.
- What is the estimate at completion (EAC) of the project?
Related Book For
Posted Date: