Question: A project has an Earned Value (EV) = $5, Actual Cost (AC) = $7 and both Cost Performance Index (CPI) and Schedule Performance Index (SPI)
- A project has an Earned Value (EV) = $5, Actual Cost (AC) = $7 and both Cost Performance Index (CPI) and Schedule Performance Index (SPI) equal 0.90. The original project budget is $10. Assuming the remaining work will be impacted by the current cost performance and current schedule performance.
- What is the estimate at completion (EAC) of the project?
Step by Step Solution
There are 3 Steps involved in it
To calculate the Estimate at Completion EAC of the project when both cost and s... View full answer
Get step-by-step solutions from verified subject matter experts
