Question: Master Production Schedule - Total Capacity Hours Available Using the data and information from the following chart, what are the Total Capacity Hours Available per

Master Production Schedule - Total Capacity Hours Available
Using the data and information from the following chart, what are the Total Capacity Hours Available per week for this manufacturing operation?
Demonstrated Weekly Capacity
Hours per Shift per Manufacturing Line
7.50
Shifts per Day per Manufacturing Line
2.0
Days per Week per Manufacturing Line
5.0
Number of Manufacturing Lines
8.0
Total Capacity Hours Available
???