Question: Master Production Scheduling: complete the following table and answer the following questions. Calculate projected inventory, MPS, and Available to Promise, out to week 7. (10-pts)

 Master Production Scheduling: complete the following table and answer the following

Master Production Scheduling: complete the following table and answer the following questions. Calculate projected inventory, MPS, and Available to Promise, out to week 7. (10-pts) Order Quantity Lot Size =100 Safety Stock =0 Beginning Inventory =500 Master Production Schedule weeks