Question: Matching ( 2 pts ea ) 2 7 . a Are we ahead of schedule 2 8 . f Hold efficiently are we using our

Matching (2 pts ea)27. a Are we ahead of schedule
28.f Hold efficiently are we using our time
29.
C
When is the project likely to be completed
30.
31.
32. g
33.
34.
35. Are we over or under budget How efficiently are we using our resources How efficiently must we use our remaining resources What is the entire project ultimately gong to be How much are we over or under budget What is the cost of the remaining work to be done.
a.CPI
b.CV
c. TCPI
d. EAC
e. EAC
f. SPI
g. VAC
h.SV
i. ETC
 Matching (2 pts ea)27. a Are we ahead of schedule 28.f