Question: Work Plan table [ [ Activity Name,Predecessor,Duration ( in days ) , Status ] , [ A , None, 4 , Completed ] ,

Work Plan
\table[[Activity Name,Predecessor,Duration (in days),Status],[A,None,4,Completed],[B,None,3,Completed],[C,B,2,Completed],[D,B,3,Completed],[E,A,3,Completed],[F,D,7,Completed],[G,C,5,Completed],[H,None,10,\table[[Half of the activity],[completed]]]]
Using a Gantt chart, answer the following project questions. You are required to create a Gantt chart next page. To create a Gantt chart, you can use MS Word or Excel. If you prefer, you can draw it manually and submit its picture.
How long (in days) does it take to complete the project? (2 points)
What are the critical activities? List the names. (2 points)
What is the slack time for the activity B?(2 points)
Assume that it is Day 7 now. Are you ahead of schedule or behind schedule for the Activity E?(1 point)
Thank you!
 Work Plan \table[[Activity Name,Predecessor,Duration (in days),Status],[A,None,4,Completed],[B,None,3,Completed],[C,B,2,Completed],[D,B,3,Completed],[E,A,3,Completed],[F,D,7,Completed],[G,C,5,Completed],[H,None,10,\table[[Half of the activity],[completed]]]] Using a

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!