Question: Material A is used as follows: Minimum Usage 500 units per week Maximum Usage 1,500 units per week Normal Usage 1,000 units per week Ordering

Material A is used as follows: Minimum Usage 500 units per week Maximum Usage 1,500 units per week Normal Usage 1,000 units per week Ordering Quantities 1,600 units Delivery Period 4 to 6 weeks Calculate : (i) Maximum Level, (ii) Minimum Level and (iii) Ordering Level
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts