Question: Two types of materials are used as follows: Minimum usage 20 units per week each Maximum usage 60 units per week each Normal usage 40

Two types of materials are used as follows:

Minimum usage 20 units per week each

Maximum usage 60 units per week each

Normal usage 40 units per week each

Re-order period or Lead time

Material A: 3 to 5 weeks

Material B: 2 to 4 weeks

Calculate reorder point for two types of materials?