Question: Material Requirements Planning Assignment The following table lists the components needed to assemble an end item, lead times ( in weeks ) , quantities on

Material Requirements Planning Assignment
The following table lists the components needed to assemble an end item, lead times (in weeks), quantities on hand, and scheduled receipts. Compete an MRP schedules sufficient to produce Item A in quantities of 20 in week two, 10 in week four, 20 in week six, 5 in week seven, 35 in week nine, and 10 in week ten. Assume all components can be ordered on a lot-for-lot basis except Item C, which has a fixed lot size of 50(can be ordered in multiples of 50 if needed).
\table[[Item,Lead Time,Amount on Hand,Scheduled Receipts,Lot Sizing],[A,2,25,,Lot-for-Lot],[B,2,22,25 in week #3,Lot-for-Lot],[C,1,4,50 in week #1,50 Fixed],[D,2,27,,Lot-for-Lot],[E,2,15,,Lot-for-Lot]]
MasterSchedule foGrossrequrementsOn handScheduled receiptsMWeekNetrequrenmentsPlanned order receiptsOuantityYPlanned order releasesGrOSS TequirementsOn handScheduled receiptsNetreqrementsPlanned order teceiptsPlanned order releasesGrOSS requirementsOn handScheduied receiptsNet requirementsPlanned order receiptsGroS#Planned order releasesOn handScheduied nenpr#Net sequisPlanned ordetPlannedo1det HeBegIny4BegInyWeekWeekBeg1234566Meek567891010124S 6910
 Material Requirements Planning Assignment The following table lists the components needed

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!