Question: Maximum capacity (labor hours): 300 hours per week Effective capacity ratio: 80% Actual time worked: 213 hours per week over the last two weeks On-time
Maximum capacity (labor hours): 300 hours per week Effective capacity ratio: 80% Actual time worked: 213 hours per week over the last two weeks On-time delivery %: 77.5 percent of the jobs are being completed on time. Calculate the effective capacity and actual utilization.
Do we need to add more capacity?