Question: MBA322 - Operations Session 9 Homework Assignment The following activities are part of a project at be scheduled using the Critical Path Method (CPM): Actiurityr

 MBA322 - Operations Session 9 Homework Assignment The following activities are

MBA322 - Operations Session 9 Homework Assignment The following activities are part of a project at be scheduled using the Critical Path Method (CPM): Actiurityr Immediate Predecessor Time (Weeks) A 3 B A 4 C A 6 D B 6 E B,C 1 F C 4 G D, E 6 H G,F 8 a. Draw the network. b. What is the critical path? c. How manyr weeks will it take to complete the project