Question: MBA322 - Operations Session 9 Homework Assignment Homework Problem #5 The R&D Department is planning to bid on a large project for the development of


MBA322 - Operations Session 9 Homework Assignment Homework Problem #5 The R&D Department is planning to bid on a large project for the development of a new braking system for commercial planes. The accompanying table shows the activities, times, and sequences required: Time in days Activity Immediate Predecessor Optimistic Most Likely Pessimistic A A C B,D SWHONGHI --IOTMOOD B 14 E, F 4 F 6 9 G 11 12 H, I 14 16 20 a. Draw the network diagram with EF, ES, LS, and LF noted. (Hint: Pick one of the three processing times above.) b. What is the critical path? C. Suppose you want to shorten the completion time as much as possible, and you have the option of shortening any or all of B, C, D, and G each one week. Which would you shorten and why