Question: me table delow siluws uetails ior a project.Create a schedule that is constrained to require no more than 5 engineers at one time. Arrange your
me table delow siluws uetails ior a project.Create a schedule that is constrained to require no more than 5 engineers at one time. Arrange your schedule to finish as early as possible within this constraint and to minimise the number of hirings and firings.Do not split or compress any activities.\table[[Activity,Predecessor,Duration,Engineers,Start Time],[A,None,1,1,],[B,None,3,1,],[C,None,5,3,],[D,B,4,4,],[E,B,2,3,],[F,B,3,4,],[G,F,1,1,],[H,E,5,3,],[I,G,5,2,],[J,F,5,1,],[K,C,3,2,],[L,A,1,1,]]All parts of the question must be answered.