Question: The table below shows details for a project. Create a schedule that is constrained to require no more than 5 engineers at one time. Arrange

The table below shows details for a project. Create a schedule that is constrained to require no more than 5 engineers at one time. Arrange your schedule to finish as early as possible
within this constraint and to minimise the number of hirings and firings. Do not split or compress any activities.
The table below shows details for a project.