Meals are cooked in a process with two resources.
Meals are cooked in a process with two resources. The processing times for the resources are 300 and 170 minutes. The first resource has 8 workers and the second resource has 10 workers. Demand occurs at the rate 1.3 Meals per hour. Instruction: Round your answer to one decimal place What is the implied utilization (%) of the second resource? 36.8%