Question: Mega Corp. is designing a product layout for a new electronic product. They plan to use this production line 8 hours a day in order

Mega Corp. is designing a product layout for a
Mega Corp. is designing a product layout for a new electronic product. They plan to use this production line 8 hours a day in order to meet demand forecast of 800 units per day, here are seven (07) tasks A, B, C, D, E, F, and G, with processing times in seconds) 34,20,10,16, 10, 20, and 38, respectively. What is the minimum number of workstations needed for the output to meet the forecast demand? Select one: a. 1 b. 2 c. 3 d. 6