Question: Mega Corp. is designing a product layout for a new electronic product. They plan to use this production line 8 hours a day in order
Mega Corp. is designing a product layout for a new electronic product. They plan to use this production line 8 hours a day in order to meet forecasted demand of 700 units per day. There are seven (o7) tasks are A, B, C, D, E, F, and G. The corresponding processing time (in seconds) are these tasks are 34, 20, 10, 16, 10, 20, and 38 respectively. How many minimum numbers of workstations are needed for output to meet the forecasted demand? Select one: a.1 b.5 C.3 d. 2