Question: mework Resource Management Hint) Check My Work Given the bill of material for the printer cartridge (A) shown below, a gross requirement to build 200

mework Resource Management Hint) Check My Work
mework Resource Management Hint) Check My Work Given the bill of material for the printer cartridge (A) shown below, a gross requirement to build 200 units of Aan on hand Inventory level for endtem A of 75 units, and assuming zero lead-times for all items AB, C, D, and compute the net requirements for each item. Assume all on-hand quantities for items B, C, D, and E are rero, Round your answers to the nearest whole number (0) Net Requirement Item A 160 110 C 50 160 35 x