Question: MGMT 4 1 8 Exercise 1 Using MS Project 2 0 2 1 , develop a network diagram for this project and understand how MS
MGMT Exercise
Using MS Project develop a network diagram for this project and understand how MS Project uses nodes to identify activity durations, start and finish dates, and predecessors. What is the critical path for this network diagram? What would be the start slack for each activity? What would be the finish slack for each activity? What could be the top three options in your mind to shorten the project duration in this specific project? Please provide your justification to support each of your options.
tableActivityTime daysPredecessorABACB FDAEDFDGE FHGIC GJIKHLJ K