Question: MGT 2 0 1 3 0 1 , 0 2 Final Exam May 2 0 2 4 2 0 points 1 . You are the

MGT 201301,02
Final Exam
May 2024
20 points
1. You are the project manager in charge of planning a student graduation party 3 months
from today. Prepare the Statement-of-Work (SOW) and Work-Breakdown-Structure
(WBS) for this project.
2. The following activities are part of a project to be scheduled using the Critical Path
Method:
Activity Immediate
Predecessor
Time
(weeks)
A 6
B A 3
C A 7
D C 2
E B, D 4
F D 3
G E, F 7
a. Draw the network of the project tasks.
b. What is the critical path (the activities on the critical path)?
c. How many weeks will it take to complete the project?
3. The following table lists the critical-path tasks of a project. Use the expected time
formula to calculate the total project schedule.
Task No. Optimistic Time
to Complete, a
Most-likely Time
to Complete, m
Pessimistic Time
to Complete, b
Expected Time
to Complete, ET
1234
2123
34512
43411
5135
Total Project Schedule
4. Avis is a car rental company and is located three miles from the Los Angeles airport
(LAX). Avis is dispatching a bus from its offices to the airport every 2 minutes. The
average traveling time (a round trip) is 20 minutes.
How many Avis buses are traveling to and from the airport?
Hint: Remember Littles Law for calculating work-in-process inventory:
Inventory = Throughput * Flowtime
5. An assembly line is to operate eight hours per day with a desired output of 240 units per
day. There are N=4 workstations and their task times are 110 sec,100 sec,120 sec, and
90 sec, respectively, for a total of T =420 sec.
a. What is the cycle time of the line, C in seconds per unit
b. What is the line efficiency?
Hint: Efficiency =
6. Poka-yoke is a Japanese term that means "mistake-proofing" or "error prevention". How
do you apply this methodology to make a service process fail-safe?
7. A cafeterias serving line has a coffee urn (percolator) from which students serve
themselves. Arrivals at the urn follow a Poisson distribution at the rate of three per
minute. In serving themselves, students take about 15 seconds, exponentially
distributed.
Arrival rate =
Service rate =
a. How many customers would you expect to see on average in the line for
coffee?
b. How long would you expect it to take to get a cup of coffee?
Remember the following equations for the length of the line and the wait time in
the line:
=
=
8. Aggregate sales and operations planning is done at three different time ranges. What
are they? Why aggregate planning is important?
9. What are the four major costs of production that should be accounted for in production
planning?
10. What do we mean by Total Quality Management in a firm?
11.The Quality Assurance Department is the primary organizational unit responsible for
the quality of the companys products and services. Do you agree with this statement?
If not, why not and then who is responsible for quality?
12. In an agreement between a supplier and a customer, the supplier must ensure that all
parts are within design tolerance before shipment to the customer. What would be the
effect of this agreement on the cost-of-quality to the customer?
13. A customer call center is evaluating customer satisfaction surveys to identify the most
prevalent quality problems in their process. Specific customer complaints have been
analyzed and grouped into eight different categories. Which quality (i.e., six sigma)
analytical tool would be most helpful to management here?

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!