Question: Michael was working on a manuscript for Gianna, who worked at a publishing house. They agreed that Michael would deliver a draft of the manuscript
Michael was working on a manuscript for Gianna, who worked at a publishing house. They agreed that Michael would deliver a draft of the manuscript to Gianna on February th
Unfortunately, Michael encountered a series of difficulties in January. His computer broke which deleted some of his work. Then, his house had a major fire which required him to move back to his parents' home in a different city. Lastly, Michael then got a terrible case of pneumonia and was unable to work at all.
If Michael delivers the manuscript to Gianna on February th is that a material breach?
Group of answer choices
Yes, time is always of the essence.
Yes, there was nothing in the contract about extending timelines due to extenuating circumstances.
No Gianna is required to give leniency due to his health problems when he had pneumonia.
No his behavior was not willful and there is no indication that Gianna needed the manuscript by February th for a specific reason.
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock