Question: Microsoft is planning to launch a new database system. Below is the process with different main processes and sub-tasks so you will end up with
Microsoft is planning to launch a new database system. Below is the process with different main processes and sub-tasks so you will end up with multiple diagrams (one for the main process and one for the subtasks).
| Activity ID | Activity | Predecessor | Duration (Days) |
| 1 | Analysis Process | - | 4 |
| 1a | On-site meetings | - | 1 |
| 1b | Discussion with shareholders | On-site meetings | 1 |
| 1c | Document current system | Discussion with shareholders | 2 |
| 2 | Design Process | Analysis Process | 20 |
| 2a | Design database | Discussion with shareholders | 5 |
| 2b | Software design | Design database | 7 |
| 2c | Interface design | Design database | 5 |
| 2d | Create design specification | Design database | 3 |
| 3 | Development Process | Design Process | 15 |
| 3a | Develop System Modules | Create design specification | 5 |
| 3b | Integrate System Modules | Develop System Modules | 4 |
| 3c | Perform Initial Testing | Integrate System Modules | 6 |
| 4 | Testing Process | Development Process | 7 |
| 4a | Perform System Testing | Perform Initial Testing | 3 |
| 4b | Document Issues Found | Perform System Testing | 1 |
| 4c | Find solutions | Document Issues Found | 3 |
| 5 | Introduce new system | Testing Process | 1 |
Instructions:
1. Create a precedence diagram model
-
Perform a forward pass and backwards pass
-
Calculate the float/slack
-
Identify the critical path
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts