Question: Microsoft Project 2 0 2 1 : Real World Scheduling Schedule Analysis - Lab # 6 Name Addee Pickett After completing Lab # 6 ,
Microsoft Project : Real World Scheduling
Schedule Analysis Lab #
Name Addee Pickett
After completing Lab # answer the following questions from the Baseline and First Update schedules in the software and from the printouts for this lab and turn the Schedule Analysis Lab # in to your instructor stapled on top of the printouts.
Baseline Schedule:
Once you start the update, which sets of dates can potentially change? circle all that apply All Baseline Dates All StartFinish Dates Only Start Dates Only Finish Dates
Once you start the update, which durations can potentially change? circle all that apply Baseline Duration Bas Dur Duration Dur Remaining Duration Rem Dur
Prior to the first update, could Baseline and Baseline be different? Yes or No
Which schedule stays "locked in forever? Baseline or Baseline circle one
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock