Question: Microsoft Project 2 0 1 6 : Real World Scheduling Schedule Analysis - Lab # 5 Name Ana Valdez After completing Lab # 5 ,

Microsoft Project 2016: Real World Scheduling
Schedule Analysis - Lab #5
Name Ana Valdez
After completing Lab #5, answer the following questions from Resource Loading, Cost Resources, and Accelerated schedules in the software and from the printouts for this lab and turn the Schedule Analysis - Lab #5 in to your instructor stapled on top of the printouts.
Resource Loading:
What is the crew cost, not including additional costs, of the Exterior Walls crew ?
Cost per day Cost per hour q,
q,
What is the average cost per hour, per crew member of the Foundation task crew ?
There is an over-allocation of 1 carpenter for 1 day on Friday, July 31st, between the Interior Walls, Exterior Sheathing, and Doors & Windows tasks. How would you recommend solving this shortage of 1 carpenter? q,4. There is an over-allocation of resources with the Interior and Exterior Finishes tasks.
Describe what resource or resources are over-allocated, list how many of each additional resource(s) are needed, and list when are they needed (from when to when)?
q, How would you recommend solving this over-allocation of the Interior and Exterior
F
t Resources:
What is the cost per day rate of the Insulation subcontractor?
The Foundation task's total cost is $131,600. Factoring in duration, crew mix, cost rates, and other additional costs, write the calculation that equals $131,600?
 Microsoft Project 2016: Real World Scheduling Schedule Analysis - Lab #5

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!