Question: Milestone 1 : Establish Plant Delivery and Logistics Plan Task 1 . 1 : Source packaging materials ( Fulfillment Director, 2 0 days ) -
Milestone : Establish Plant Delivery and Logistics Plan
Task : Source packaging materials Fulfillment Director, days Predecessor: None
Task : Hire delivery drivers Human Resources Specialist, days Predecessor:
None
Task : Calculate delivery fees Financial Analyst, days Predecessor: Task
Milestone : Select and Install Supply Chain Software and Equipment
Task : Supervise vendor setup of inventory management and fulfillment software
Inventory Manager, days Predecessor: None
Task : Supervise vendor installation of fulfillment equipment Fulfillment Director,
days Predecessor: Task
Task : Establish internal safety protocols for equipment Quality Assurance Tester,
days Predecessor: Task
Milestone : Develop and Launch Employee Training Program
Task : Develop training sessions Human Resources Specialist, days Predecessor:
Task
Task : Train employees to use the software and equipment Training Manager, days
Predecessor: Task
Task : Monitor progress and improve training processes Training Manager, days
Predecessor: Task
For each task, include the following in your WBS submission:
Milestone: The major phase or objective under which the task falls.
ID: A unique identifier for each task.
Task: A description of the specific work or activity to be completed.
Owner: The individual responsible for overseeing or completing the task
Duration in days: The estimated time required to complete the task.
Predecessor: The task that must be completed before the current task can begin. Use
"None" if the task has no predecesso
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock