Question: Min- Most Max- Activity Predecessors Mean Variance ES LS Slack imum Likely imum A Get equipment 3 5 7 None B Hire people 4 4


Min- Most Max- Activity Predecessors Mean Variance ES LS Slack imum Likely imum A Get equipment 3 5 7 None B Hire people 4 4 4 None C Develop system 12 15 24 A, B D Develop training 3 3 9 C program E Documentation 4 6 14 C F Install system 6 9 18 D, E