Question: ( mind: here the total cost after crash includes the normal cost and crashed cost ) What is the lowest cost to complete this project

(mind: here the total cost after crash includes the normal cost and crashed cost)
What is the lowest cost to complete this project in 70 weeks?
So cost to crash unit day
A: (4000-2000)/(10-7)=667
B: (3000-1000)/(5-2)=667
C: (4500-3000)/(12-9)=500