Question: MIS Design Project: Part 1 Draw the project network, take a picture and upload it. MIS Design Project: Part 2 What is the critical path

MIS Design Project: Part 1
Draw the project network, take a picture and upload it.
MIS Design Project: Part 2
What is the critical path for this project? Can they complete the project in the 38 days remaining until the end of the semester?
MIS Design Project: Introduction The following 2 questions refer to the following information: A senior MIS design class project team has developed the following schedule of activities for their project, using their best estimate of completion times (in days). Both written and oral reports are required. Activity Label Time Immediate Predecessor Find Client A 4 Write Prospectus B 2 A Obtain Approval from Client and Professor C 3 B Complete Programming D 12 Do Industry Background Research E 10 Write Final Paper F 6 DE Write Oral Report G 5 D, EStep by Step Solution