Question: MKT 3 6 4 - Operations Management Case # 1 - Project Management Southwestern University is constructing a new building and needs to use Project

MKT 364- Operations Management
Case #1- Project Management
Southwestern University is constructing a new building and needs to use Project Management techniques to ensure the project stays on schedule and on budget. Use the below charts to solve the questions on the following page.
\table[[Activity,Description,Predecessor(s)],[A,Bonding, Insurance, tax structuring,-],[B,Foundation, concrete footings for boxes,A],[C,Upgrading skybox stadium seating,A],[D,Upgrading walkways, stairwells, elevators,C],[E,Interior wiring, lathes,B],[F,Inspection approvals,E],[G,Plumbing,D, F],[H,Painting,G],[I,Hardware / AC / metal workings,H],[J,Tile / carpet / windows,H],[K,Inspection,J
\table[[,Time Estimates (Days),],[Activity,Optimistic,\table[[Most],[Likely]],Pessimistic,\table[[Crash Cost],[/ Day]]],[A,20,30,40,1,500],[B,20,65,80,3,500],[C,50,60,100,4,000],[D,30,50,100,1,900],[E,25,30,35,9,500],[F,0.1,0.1,0.1,-],[G,25,30,35,2,500],[H,10,20,30,2,000],[I,20,25,60,2,000],[J,8,10,12,6,000],[K,0.1,0.1,0.1,-],[L,20,25,60,4,500]]
Solution Requirements
Utilize Microsoft Excel to complete the following steps:
Draw the project network diagram.
Calculate the expected activity time, standard deviation, and variance for each activity. Create a table to display the results.
Find the critical path Utilize a forward and backward pass analysis. Create a table to display ES,EF,LS,LF, and slack Calculate the expected project completion time and the standard deviation of the critical path. Use the expected time activity time in your calculations.
Find the probability of completing in 270 days.
Examine the possibility of crashing the project to 250 and 240 days. In order to do this, use the optimistic time as the crash time, and calculate the lowest possible total cost of crashing using the cost per day. The crash cost/day is given to you in the chart.
Prowide recommendations to managers of actions that should be pursued. Share your own insights that you discowered while solving the problem.],[L,Final detail work / cleanup,I, K]]
 MKT 364- Operations Management Case #1- Project Management Southwestern University is

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!