Question: MKT 3 6 4 Operations Management Case # 1 Project Management Southwestern University is constructing a new building and needs to use Project Management techniques

MKT 364 Operations Management
Case #1 Project Management
Southwestern University is constructing a new building and needs to use Project Management techniques to ensure the project stays on schedule and on budget. Use the below charts to solve the questions on the following page.
Activity Description Predecessor(s)
A Bonding, Insurance, tax structuring -
B Foundation, concrete footings for boxes A
C Upgrading skybox stadium seating A
D Upgrading walkways, stairwells, elevators C
E Interior wiring, lathes B
F Inspection approvals E
G Plumbing D, F
H Painting G
I Hardware / AC / metal workings H
J Tile / carpet / windows H
K Inspection J
L Final detail work / cleanup I, K
Time Estimates (Days)
Activity Optimistic Most Likely Pessimistic Crash Cost / Day
A 2030401,500
B 2065803,500
C 50601004,000
D 30501001,900
E 2530359,500
F 0.10.10.1-
G 2530352,500
H 1020302,000
I 2025602,000
J 810126,000
K 0.10.10.1-
L 2025604,500

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!