Question: Module 4 Exam, Part II 1) The following data is received from your contractor on a key component of the project: Budgeted Cost of Work


Module 4 Exam, Part II 1) The following data is received from your contractor on a key component of the project: Budgeted Cost of Work Performed (BCWP) = $300 Budgeted Cost of Work Scheduled (BCWS) = $200 Actual Cost of Work Performed (ACWP) = $500 Which of the following Earned Value Management (EVM) metrics can be determined from these data? O CV = - $200 and SV = $100 O % Spent = 66% and % Complete = 50% O CPI = 1.67 and SPI = 0.67 O Cost Variance (CV) = $200 and Schedule Variance (SV) = - $100