Question: Monitors for these computing systems are a Level 1 item and each computer receives only one monitor. Using a lead time of one week, what

Monitors for these computing systems are a Level 1 item and each computer receives only one monitor.
Using a lead time of one week, what are the Level 1 Gross Requirements for Monitors? Assume any inventory on hand will be used as soon a possible.
1100 in week 3,600 in week 4,300 in week 5
1100 in week 2,600 in week 3,300 in week 4
500 in week 1,600 in week 2,200 in week 3
500 in week 2,600 in week 3,200 in week 4
Impossible to determine from this information