Question: More info *** Activity . B C D E Oowo Duration (days) 6 3.5 7 6 6.5 7 3.5 Predecessors None None A A, B

More info *** Activity . B C D E Oowo Duration
More info *** Activity . B C D E Oowo Duration
More info *** Activity . B C D E Oowo Duration
More info *** Activity . B C D E Oowo Duration (days) 6 3.5 7 6 6.5 7 3.5 Predecessors None None A A, B C D D E, F F G Print Done b. Identity all the paths through the network and their lengths. Fill in the table below (enter your responses rounded to ono decimal place). Path Length (days) A-C A- VEG A- V-G OOOOO -E-G B V-G c. The critical activities are V so they make up the critical path A- -G VE-G B- VG c. The critical activities are so they make up the critical path The entire project will take days to complete. (Enter your response rounded to one decimal place) d. Management would like to complete the project in less than 16 days. Management has determined that activity can be crashed 5 days, for a total cost of $7,500. No other activities can be crashed After crashing is the critical path. The entire project will take days. (Enter your response rounded to one decimal place.) Crashing activity E moet management's goal of less than 16 days

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!