7. Given the project within the table below,
7. Given the project within the table below, calculate the following: a. The critical path b. The minimum project duration C. The amount of slack for each activity Activity A B C D E Duration (hours) 4 3 10 7 1 11 15 Immediate Predecessors None None None BC D E AF