Question: Motors are assembled in a process with two sequential resources. The processing times for the resources are 9.00 and 13.00 minutes. Instruction: Round your answer

Motors are assembled in a process with two sequential resources. The processing times for the resources are 9.00 and 13.00 minutes.

Instruction: Round your answer to 2 decimal places.

What is the capacity of this process in terms of motors per hour? ____ motors per hour