Question: Shirts are made in a process with two sequential resources. The processing times for the resources are 6.30 and 3.50 minutes. Instruction Round your answer

Shirts are made in a process with two sequential resources. The processing times for the resources are 6.30 and 3.50 minutes. Instruction Round your answer to 2 decimal places. What is the capacity of this process in terms of shirts per hour? 9.52 shirts per hour