Question: Moving to another question will save this response. 15 points estion 3 A project to develop technology training seminars is 5 days behind schedule on

Moving to another question will save this
Moving to another question will save this response. 15 points estion 3 A project to develop technology training seminars is 5 days behind schedule on day 65 It had a planned cost of $735,000 for this point in time, but the actual cost is only 5550.000 Aabe completed is $678,000. Estimate the schedule and cost variances. Re-estimate the variances of the actual cost had been $750,000 Arial "3 (121) PEET T' T. TTTT Paragraph %DOQI Sx Mashups - 1 4 Path P Moving to another question will save this response