Question: > Moving to another question will save this response. Question 27 of 3 uestion 27 4 points (CH 7) A project was estimated to cost

> Moving to another question will save this
> Moving to another question will save this response. Question 27 of 3 uestion 27 4 points (CH 7) A project was estimated to cost AED 1.5M and scheduled to last for 6 months. After three months, what would be the schedule Variance given the following earned value analysis in AEDT EV - AED 650,000 PV - AED 750,000; AC - AID 100,000 a. -100,000 Ob. +100,000 OC -50,000 O d. 50,000 Question 27 Moving to another question will save this response. Cone W