Question: 26 Moving to another question will save this response Question 27 ICH 7) A project was estimated to cost AED 1.5M and scheduled to last

 26 Moving to another question will save this response Question 27

26 Moving to another question will save this response Question 27 ICH 7) A project was estimated to cost AED 1.5M and scheduled to last for months. After three months, what would be the cost Variance en the following and value analysis in AED? EV - AED 50.000 PV - AED 750.000 AC = AED 800.000 - 150.000 b. 150.000 650.000 050.000 Moving to another question will save this response. VO