Question: Moving to another question will save this response. Question 280 Question 28 4.5 points Sa There are five activities on a project's critical path and

Moving to another question will save this

Moving to another question will save this response. Question 280 Question 28 4.5 points Sa There are five activities on a project's critical path and they have standard deviations of 1, 1, 3, 5, 5 days. The standard deviation (in days) of the critical path is: > > O A. 4.6 B. 9.8 O C. 8.8 O D. 7.8 E. 10.2 O F. 10.6 L Moving to another question will save this response. Question 28