Question: Moving to another question will save this response Question 39 of 60 Question 39 0.67 points Save Answer In making a backward pass through a

Moving to another question will save this response Question 39 of 60 Question 39 0.67 points Save Answer In making a backward pass through a network, activity Lhas an activity time of 4 and immediately precedes activities M. P. and T. The late start times for activities M, P. and T are 22, 17, and 27. respectively. The late finish times for activities M. P. and Tare 20. 27. and 33, respectively What is the late finish time for activity L? O A 13 OB 17 OC 22 0.33