Question: Moving to the next question prevents changes to this answer. Question 20 Which of the following activities isn't part of the schedule management knowledge
Moving to the next question prevents changes to this answer. Question 20 Which of the following activities isn't part of the schedule management knowledge area? Identifying the type and quantity of resources that will be required for each activity Organizing the activities and milestones in the order in which the work will be performed Estimating the amount of time required to complete each activity Decomposing the work packages created in the WBS into the activities required to produce the work package deliverables Moving to the next question prevents changes to this answer. DELL