Question: Moving to the next question prevents changes to this answer. Qu stion 2 C 1 = 5 0 0 + 5 . 3 P 1

Moving to the next question prevents changes to this answer.
Qustion 2
C1=500+5.3P1+0.004P12
C2=400+5.5P2+0.006P22
C3=200+5.8P3+0.009P32
Where P1,P2, and P3 are in MW. The total power demand is PD=1200MW.
Neglecting line losses and generator limits.
Determine the optimal scheduling of generation P2