Question: MPS Problems 1-5 are based on same data. Period 1 2 3 4 5 6 Forecast 200 200 200 200 200 200 Orders 160 140
MPS Problems 1-5 are based on same data.
| Period | 1 | 2 | 3 | 4 | 5 | 6 |
| Forecast | 200 | 200 | 200 | 200 | 200 | 200 |
| Orders | 160 | 140 | 100 | 0 | 0 | 0 |
| Projected Available Balance (On hand 300) | ??? | ??? |
|
|
|
|
| Available to Promise |
|
|
|
|
|
|
| MPS |
| 500 |
|
| 500 |
|
What is the projected available balance in PERIOD 1?
What is the projected available balance in PERIOD 2?
What is the projected available balance in PERIOD 5?
What is the available to promise (discrete) in PERIOD 1?
What is the available to promise (discrete) in PERIOD 5?