Question: Mr. Foster used the same approach in computing G & A as he had for the manufacturing burden. The contractor had used 6% in his
Mr. Foster used the same approach in computing G & A as he had for the manufacturing burden. The contractor had used 6% in his original estimate and Mr. Foster thought that the same rate should be used in pricing the change. J
QUESTIONS:
15. Do you agree with this approach?
16. If the situation was reversed, viz.; the contractor had used a G&A rate of 15% in his original proposal, and his anticipated G&A rate during, the period of performance of the changed work was 6%, would you approach the matter any differently?