Question: MRP Problem Using the information given below, develop a complete MRP material plan. The gross requirements for scooters are 5 0 units in week 7

MRP Problem
Using the information given below, develop a complete MRP material plan. The gross requirements for scooters are 50 units in week 7 and 60 units in week 8.
Item Quantity on Hand Lead Time
Scooter 201 week
Base 43 week
Handle 102 weeks
Wheel Assembly 01 week
Wheels 123 weeks