Question: Using the information provided below, develop a Material Requirements Plan ( MRP ) . The gross requirements for cars are 5 , 0 0 0

Using the information provided below, develop a Material Requirements Plan (MRP). The gross requirements for cars are 5,000 units in week 7 and 7,500 units in week 8.
The following information is provided for items, quantity on hand, and lead times.
Item
Quantity on Hand
Lead Time
Car
2500
1 week
Frame
1000
4 weeks
Powertrain
2000
3 weeks
Motor
500
1 week
Spark Plugs
12000
2 weeks
The Level 1 item is "Car."
The Frame, Powertrain, and Motor are Level 2 items. One (1) of each is needed for the Car.
Spark Plugs are a Level 3 item required for the Motor. There are eight (8) Spark Plugs needed for each Motor.
Use the results of your analysis to answer the next 5 questions on MRP.
Flag question: Question 10
Question 102 pts
After completing the MRP, the Gross requirements for "Frames" in week 6 is:
Group of answer choices
1,000
5,000
1,500
2,500
Flag question: Question 11
Question 112 pts
After calculating the MRP, the total Net requirements for "Power train is:
Group of answer choices
10,000
15,000
2,000
3,000
8,000
Flag question: Question 12
Question 122 pts
The "Gross requirement" for "Motor" in Week 7 is:
Group of answer choices
4,500
9,500
2,000
7,500
15,000
Flag question: Question 13
Question 132 pts
After completing the MRP, the first Planned order releases for Spark Plugs is for ______________ spark plugs.
Group of answer choices
60,000
3,000
12,000
4,000
64,000
Flag question: Question 14
Question 142 pts
After completing the MRP, the first Planned Order Release for the Spark Plugs occurs during Week ______.
Group of answer choices
Four
Five
Six
Three
Two

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!