Question: MRP Processing - Sample Given the following information and MRP table for part D ; 1 - Currently, there are 2 4 0 on -
MRP Processing Sample
Given the following information and MRP table for part
Currently, there are onhand inventory.
There will be a previously arranged scheduled receipt of units of part at the beginning of week
Lotforlot ordering is used.
Lead time is one week.
Determine the size and timing of the planned order release necessary to meet delivery requirement: