Question: MRP Question X A(2) B(1) C(3) C(2) D(1) Item On Hand Lead Time (Weeks) X 50 2 A 75 3 B 25 1 C 10
MRP Question
X
A(2) B(1)
C(3) C(2) D(1)
| Item | On Hand | Lead Time (Weeks) |
| X | 50 | 2 |
| A | 75 | 3 |
| B | 25 | 1 |
| C | 10 | 2 |
| D | 20 | 2 |
Requirements include 95 units (80 firm orders and 15 forecast) of X in week 10.