Question: Multi-Part Problem: Resource Planning-AggPlan Given next 6 months aggregated demand forecast and other related information in the following tables. Month Project Demand (unit) Regular Overtime
Multi-Part Problem: Resource Planning-AggPlan Given next 6 months aggregated demand forecast and other related information in the following tables.
| Month | Project Demand (unit) |
| Regular | Overtime | Subcontract | |
| Jan | 200 | Operation Cost (unit) | $100 | $130 | $150 | |
| Feb | 200 | Capcity/month (unit) | 200 | 60 | 120 | |
| Mar | 300 | Capcity/6 month (unit) | 1200 | 360 | 720 | |
| Apr | 400 | 2280 | ||||
| May | 500 | |||||
| Jun | 200 | Other costs (unit) | ||||
| Total | 1800 | Inventory/month | $10 | |||
| Backorder/month | $30 | |||||
| Inventory (unit) | ||||||
| Given Beginning | 50 | |||||
| End of Month 6 (Required) | 100 | |||||
- Assume that you are required to use all the Regular Production Capacity, develop a Feasible Aggregate Plan, that is, an aggregate plan that meets the inventory requirements.
- Given the aggregate plan you developed in part a), Can you conclude whether or not this plan is optimal? If it is not, revise your plan to improve it. Explain why do you think the revised is better than your original one.