Question: Multiple Choice Question There are five ending activities M, N, O, P, and R with EF(M) = 12; EF(N) = 10; EF(O)=14; EF(P) = 11,

Multiple Choice Question There are five ending activities M, N, O, P, and R with EF(M) = 12; EF(N) = 10; EF(O)=14; EF(P) = 11, and EF(R) = 13. What is the project completion time? Multiple choice question. 14 The average EF Cannot be defined 10